    Coega Steels - New transformer

    The arrival of two power transformers at Coega Steels marks a significant milestone in the Nelson Mandela Bay company’s journey to self-sustainability.

    The brand-new units, manufactured in China, reached Gqeberha in July, with the first going online in September.

    This comes only months after the firm completed the largest commercial solar project in the Eastern Cape.

    The 11 484 newly installed panels generate up to 7 MW of electricity, another step forward in the steelmaker’s ongoing efforts to offset the industry’s energy demands.

    Coega Steels recycles scrap metal into what is globally referred to as “green steel” because the manufacturing process is more environmentally friendly than that of traditional coal-fired smelters.

    According to a company spokesperson, it took meticulous planning to design the transformers and have them manufactured, delivered and installed by the due date.

    Both had to be custom-made to the exact specifications outlined by the Gqeberha-based mini-mill.

    The first step was to shortlist manufacturers worldwide.

    Coega Steels then had to approve the prototype design before the units could go into production.

    “It takes four to five months to manufacture one transformer and about 45 days to be shipped to the Bay,” the spokesperson said.

    The entire operation could take up to nine months.

    When the plant’s transformer unexpectedly failed in August last year and put the livelihoods of roughly 600 employees at risk, the metro leased the steelmaker a spare unit for 12 months.

    This gave its largest electricity customer enough time to source a suitable replacement.

    Two units arrived in separate shipments, around four weeks apart, after which the leased unit was removed and returned to the municipality.

    “We have written a letter conveying our sincere gratitude to the city,” the spokesperson said.

    Installing, testing and energising the first transformer began in August and took around 15 days to complete.

    The steel manufacturer decided to commission a second to provide “redundancy” in the event of an unexpected failure.

    It should be operational towards the end of the first quarter of 2027. Once online, the transformers will operate concurrently.

    “It is purely to mitigate risk to the plant and the company’s employees,” the spokesperson said.

    For more articles like this click here.  

    If you enjoyed this website then check out our other sites: Wedding and Function, Home Food and Travel, Kids Connection, Thirsty Traveler, Bargain Buys, Boat Trips for Africa. 

    Need help with your online marketing then visit Agency One

    Facebook
    Twitter
    LinkedIn
    Pinterest